Application background

Apply here in the official call to form the Special Register of Companies.

OFFICIAL NAME OF THE PROJECT

Construction of the International Antarctic Center, XII Region

LOCATION

Sector Punta Arenosa, Punta Arenas

ARCHITECTS

Alberto Moletto – Cristóbal Tirado – Sebastián Hernández – Danilo Lagos

AREA TO BE BUILT

32.930,90 m2

FINANCIAL INSTITUTION

Gobierno Regional de Magallanes y de la Antártica Chilena

TECHNICAL UNIT

Dirección de Arquitectura del Ministerio de Obras Públicas

CONTRACTING MODALITY

Suma alzada, sin reajuste, sin anticipo.

WORK EXECUTION PERIOD

1,080 calendar days (36 months).

1

Call for the formation of a Special Registry of Companies.

March 03/22
2

Resolution approving Special Registry of Companies.

May 04/22
3

Publication in official gazette of the call for bids for the construction of the CAI.

June 6/22
4

Opening of Technical Proposals.

September 09/22
5

Resolution awarding the contract.

December 12/22
6

Contract termination.

January 01/25